Latest Projects
zoom Quechan Hotel and Casino
zoom The Trails
zoom UCSD Student Housing DB
zoom Fashion Walk
zoom Promenada at Rainbow
zoom The Village At Morena Vista
zoom Naval Medical Center Parking Garage

 

Structuaral Concrete. An inspiration to the rest of the building.
The Trails
With Convergent, Inc.
  • Subterranean garages for apartment complex, 6 buildings
  • Concrete foundations and slab, columns, CIP decks, shotcrete walls, PT and reinforcing
  • 5.5 month contract duration (5 month actual)


The Project:

KD Development sought the expertise of TB Penick to design-build the subterranean parking garages at The Trails apartments in San Diego. From pre-con through building Penick was called on to provide analytical thinking, creative techniques and efficient project management to optimize the design and construction phases. Despite several hitches, including rain delays and a tight job site, Penick executed flawlessly and finished the project ahead of schedule.

David Tichiaz, Project Manager for KD Development commended the entire TB Penick team for their positive, professional, and supportive attitude and perseverance in optimizing the construction schedule.